Erickson Avenue/Stone Spring Road begins!

Thanh -- February 15th, 2009

The City’s long anticipated Erickson Avenue/ Stone Spring Road Project began on February 9. On February 10, Public Works staff gave a presentation to City Council providing descriptions of each project phase, updates on cost and funding, and anticipated impacts to traffic during Phase I of construction.

For many years the Erickson Avenue/ Stone Spring Road Project has been identified as a top priority to improve street system connectivity, provide better east to west mobility, and address deficient capacity and critical safety concerns in the southern portion of the City of Harrisonburg. Initial conceptual planning for this project began in the late 1980s. In the mid 1990s, the City entered into contract with Mattern & Craig, Inc. to perform design and engineering services.

The Erickson Avenue/ Stone Spring Road Connection spans 3.1-miles stretching from west city limits to east city limits, providing the only continuous transportation link other than Route 33. This route provides an alternative for traffic that must currently wind through residential areas.  This project is included in the City of Harrisonburg’s 2004 Comprehensive Plan and Harrisonburg Rockingham Metropolitan Planning Organization’s (HRMPO) 2030 Transportation Plan adopted in 2005. The corridor project is also included in the current State Transportation Improvement Program (STIP) and the Six-Year Improvement Plan (SYIP). 

The corridor passes through existing fully developed commercial areas and areas currently receiving extreme interest for future residential development. The proposed corridor improvements will facilitate access to Harrisonburg High School, Stone Spring Elementary School, Berea Christian School, Ramblewood Field (a City recreational facility), Blacks Run Greenway (a City-programmed trail facility), plus an alternative route to the relocation site of the new Rockingham Memorial Hospital.

The project is divided into four phases. Funds for the construction project are from a combination of Local Funds, plus State and Federal Urban Transportation Funds.  

The update to City Council describes that the Phase I construction contract has been awarded to Perry Engineering Company, Inc. of Winchester, Virginia for an amount of $5.7 million. Additional estimates for administrative overhead, inspection, materials certification, and engineering support is $2.2. Construction estimates for all four phases of the project, excluding the bridge over I-81 (by VDOT) and the 30″ raw waterline project, totals $40,000,000.

Additionally, Phase I construction will include the eventual removal of the railroad trestle on Erickson Avenue, relocation of the railroad, and relocation of existing Pear Street. Major impacts to traffic patterns (i.e. detours) are not expected until later this summer.

The estimated completion date for construction of the entire project is late 2014, which is largely dependent upon the future availability of funds.

Additional project information can be found at www.ericksonstonespring.org.

6 Responses to “Erickson Avenue/Stone Spring Road begins!”

  1. Breslau says:

    This sounds outstandingly ambitious. Please update us on this whenever you can, Thanh.

  2. Thanh says:

    Breslau, I’m not sure what you are asking. As the project continues, citizens can continue to read updates and additional information at http://www.ericksonstonespring.org.

  3. Renee says:

    One one hand, it’s about time! But on another hand, I didn’t realize it was starting so soon! I’m looking forward to having a quicker way to cross town!

  4. Thanh says:

    And yes Breslau, I think I have to agree that this project is quite *ambitious*. I’m sure that for the people who had worked on this project during its inception in the 1980s and for those who have reviewed it as it progressed (i.e. the many City Councils), its *amazing* also that its broken ground! :)

  5. Frank Moran says:

    Where do you think the Rockingham County portion of Stone Spring will go once the city stops at Peach Grove Ave.? Is it likely the existing Stone Spring Rd. will merely be widened and come out where it does now on Port Republic Rd, or do you anticipate a new more South East route to terminate by the new Hospital site on Port Republic Rd?

  6. Rick Bowman says:

    Where can I find the proposed plan for the underpass? Will Ericson rise to the height of the rails, or will it be diverted to another crossing point?

Reader Tweets

Latest Flickr photos in the hburgnews Flickr pool
Announcements & Press Releases
  • Friendly City Grand Opening Set for July 9

    Friendly City Food Co-Op, Harrisonburg’s consumer-owned grocery, invites the community to come see its new destination for natural, organic and locally-produced products at the store’s grand opening 11 a.m.-5 p.m. July 9 at 150 East Wolfe Street.

  • Friendly City Becomes Member of National Cooperative Grocers Association

    HARRISONBURG, VA — Friendly City Food Co-op, slated to open this month in Harrisonburg, Va., has become the newest member of the National Cooperative Grocers Association (NCGA), a business services cooperative serving 120 consumer-owned food co-ops nationwide.

  • Harrisonburg Recognized as a Bike Friendly Community

    May 2: Harrisonburg was honored when the League of American Bicyclists announced the latest round of Bicycle Friendly Community (BFC) designations over the weekend to kick off May as National Bike Month.